  • Design-Build Project

  • Remove current 5kV to 120/208-volt feed to building.

  • Coordinate with utility company and install new vault, metering, and medium voltage feeders for utility company 34kV to 277/480-volt transformer.

  • Route new 480-volt underground feeders to new 480-volt to 120/208-volt transformer and re-feed existing building 208-volt switch gear.

  • Install two (2) dual port Level 3 vehicle chargers on concrete pads and route underground 480-volt feed.

  • Install two (2) single port Level 2 vehicle chargers wall mounted.

  • Energize and startup support.